Justice WILLETT delivered the opinion of the Court.
This complex case poses several vexing questions regarding Texas utility-deregulation laws and the Public Utility Commission's application of those laws. In short, numerous parties—the State of Texas, utility companies, municipal groups, consumer groups, and others—challenge the Commission's interpretations of various cost-recovery provisions in Chapter 39 of the Utilities Code. As detailed below, we affirm the court of appeals' judgment in part, reverse it in part, and remand to the PUC for further proceedings consistent with this opinion.
The Legislature in 1999
The Legislature recognized that utilities had made investments in power-generation assets that produced a reasonable return under the existing regulated environment "but might well become uneconomic and thus unrecoverable in a competitive, deregulated electric power market."
The Act deregulated the market in phases. Retail rates were frozen from September 1, 1999 until January 1, 2002.
Section 39.201 directed transmission and distribution utilities to file, on or before April 1, 2000, proposed tariffs that included "nonbypassable delivery charges" to retail electric providers.
Under Section 39.262, utilities were required, after January 10, 2004, to file with the PUC a reconciliation of stranded costs and the previous estimate of stranded costs that had been used in determining rates under Section 39.201.
From January 1, 2002 until January 1, 2007, affiliated retail electric providers were required to charge rates six percent below average rates that were in effect on January 1, 1999, subject to certain adjustments including a fuel factor.
To foster competition, utilities or their unbundled power-generation companies were required, at least 60 days before January 1, 2002, to conduct a "capacity auction" that sold entitlements to at least 15 percent of the utilities' generation capacity.
Under Section 39.262(d), the Act directs the affiliated power-generation company at the true-up proceeding to reconcile and either bill or credit the transmission and distribution utility for the net sum of (1) the former integrated utility's final fuel balance,
Section 39.262(e) directs the affiliated retail electric provider at the true-up proceeding to credit the affiliated transmission and distribution utility for "any positive difference between the price to beat under Section 39.202, reduced by the nonbypassable delivery charge established under 39.201, and the prevailing market price of electricity during the same time period."
Pursuant to Chapter 39, Reliant Energy, Inc., an integrated electric utility, separated into three entities:
These three entities filed an application with the PUC to determine stranded costs and other true-up balances pursuant to Section 39.262.
CenterPoint and various intervenors appealed the Order to district court. The district court affirmed the Order except as to two issues, one of which, concerning the capacity auction true-up, is discussed below. Both sides appealed to the court of appeals,
Generally, "[a]ny party to a proceeding before the commission is entitled to judicial review under the substantial evidence rule."
The APA also provides in Section 2001.174 that, under substantial evidence review, the court may reverse the agency's order where the agency has made a prejudicial error of law,
By statutory definition, stranded costs are based on the difference between the book value of generation assets and the market value of these assets.
Section 39.262(h) provides that the affiliated power-generation company shall establish the market value of its generation assets using one or more of four methods: the sale of assets method, the stock valuation method, the partial stock valuation (PSV) method, and the exchange of assets method.
CenterPoint complains that the PUC erred in refusing to employ the PSV method. CenterPoint attempted to establish the market value of its generation assets and resulting stranded costs under this
CenterPoint contends that the PSV method was appropriately employed because CenterPoint distributed 19.0447 percent of Genco stock to CenterPoint shareholders, and retained ownership of the rest, on January 6, 2003. CenterPoint listed Genco on the New York Stock Exchange, where the stock publicly traded. CenterPoint contends and offered evidence that it chose a stock dividend to existing shareholders in lieu of an initial public offering (IPO) because market conditions at the time would have made an IPO difficult. It further contends and offered evidence that it sold slightly over 19 percent of the stock because that percentage complied with the statute and also allowed CenterPoint and Genco to benefit from consolidated tax returns. A parent and subsidiary may file consolidated returns if the parent owns at least 80 percent of the stock in the subsidiary.
The Commission conceded in its Order that it "may not substitute its judgment for a properly conducted market valuation of generation assets determined under PURA §§ 39.262(h) and (i)." It further recognized that utilities are "required to follow one of the four methods in PURA § 39.262(h) to determine the market value of generation assets for purposes of stranded-cost recovery." Section 39.252(a) indeed provides that a utility is "allowed to recover all of its net, verifiable, nonmitigable stranded costs," but Section 39.252(d) makes clear that "nothing in this section authorizes the commission to substitute its judgment for a market valuation of generation assets determined under Sections 39.262(h) and (i)."
Nevertheless, the PUC concluded that the PSV method could not be employed by CenterPoint. The PUC noted a lack of proof that 19 percent of Genco shares had ever been sold on a national exchange. Focusing on the statutory language that the PSV method relies on a block of stock that "is spun off and sold to public investors through a national stock exchange," it concluded that while the required amount of stock was "spun off" to public investors, it was not "sold" to public investors. It
Because the PUC found that the PSV method could not be used and that no other statutorily prescribed method was available, it embarked on an effort to establish market value based on a number of "data points," including the announced sale of Genco (discussed below), market value estimates chosen by the valuation panel convened under subsection (h)(3), and other information. The valuation reached using this hybrid method resulted in a stranded cost recovery $258 million smaller than the recovery requested by CenterPoint under the PSV method. On this issue, the trial court and the court of appeals
CenterPoint, on the other hand, reads the statute to require that (1) 19 percent of Genco's stock be spun off, and (2) this block trade on a national exchange. It contends that so long as this block is publicly traded, it is being "sold to public investors through a national exchange" under the statute, and the market value of all of Genco's stock can be determined, subject to a control premium adjustment for the retained interest as provided in the statute.
The PUC argues that CenterPoint failed to prove that 19 percent of Genco's common stock sold on a national stock exchange. Assuming that this is a statutory requirement for the partial stock valuation method, it would be satisfied if the spin-off
Like CenterPoint, Intervenors contend that the PUC acted outside of its statutory authority in determining fair market value under a method not prescribed in Section
During the true-up proceeding, under a signed agreement dated July 21, 2004, CenterPoint agreed to sell Genco, which held all of the joint applicants' generating assets, to private equity firms. This agreement, styled the "Transaction Agreement," was made known to the PUC and admitted into the administrative record. The Genco shares held by CenterPoint were sold for $45.25 per share and other shares sold for $47 per share. These prices are higher than the value of $42,425 per share chosen by the PUC under its extra-statutory method of determining fair market value. They are also higher than the price of $36.26 (plus a control premium of up to 10 percent) applicable to the PSV method. Intervenors urged the PUC to reject the use of the PSV method and to either deny any stranded cost recovery or to use the announced sale of Genco under the Transaction Agreement to determine stranded costs. They argue that the Transaction Agreement was a definitive agreement to sell the assets and was made months before the final Order issued on December 17, 2004. They contend that if the Transaction Agreement is used to determine the market value of the generation assets under the sale of assets method, the resultant market value is $253 million higher than the market value determined by the PUC, and the stranded cost recovery should be reduced by this same amount.
Although acknowledging the existence of the Transaction Agreement, the PUC concluded that "[t]he announced sale of [Genco] does not constitute a sale of assets under PURA § 39.262(h)(1) because the sale is not final and there is not sufficient evidence in the record to establish under the statute that the sale is a bona fide third-party transaction under a competitive offering."
We agree with Intervenors and Center-Point that the PUC should not have used the extra-statutory method it employed in calculating market value. Section 39.262(h) specifies the permitted methods for determining market value. We need not decide if the PSV method could have been used if Genco had not been sold to private investors under the Transaction Agreement. Given that Genco actually did sell under that Agreement, we hold that the PUC should have used the sale of assets method to determine market value. There is no dispute that the Transaction Agreement closed under its terms and Genco was sold to new owners.
On remand the Commission should use the sale of assets method to determine market value. For several reasons Chapter 39 compels the use of this method in this case. First, Chapter 39 recognizes and the PUC Order repeatedly acknowledged in both its findings of fact and conclusions of law that "[m]arket value is defined as the value the assets would have if bought and sold in a bona fide third-party transaction on the open market under PURA § 39.262(h)." Section 39.251(4) indeed defines market value using these exact words. While other methods are provided to determine market value indirectly, we think the actual sale of all the generation assets under the Transaction Agreement provides the best measure of market value.
Second, since CenterPoint succeeded in selling Genco for an amount greater than the value of the company as measured by the PSV method or the extra-statutory method employed by the PUC, Center-Point achieved a higher market value for the assets by completing the transaction than the market value derived from other methods. This higher market value translates to a lower measure of stranded costs, and is consistent with the utility's duty under Section 39.252(d) to "pursue commercially reasonable means to reduce its potential stranded costs," with Section 39.252(a)'s recognition that a utility should recover only "nonmitigable stranded costs," and with Section 39.262(a)'s requirement that utilities "may not be permitted to overrecover stranded costs through the procedures established by this section." CenterPoint reduced its stranded costs by executing and fully performing under the Transaction Agreement. The Commission should not ignore that agreement unless it had a sound factual or legal reason to do so, and none appears in this case. CenterPoint's own chief executive testified that "we're not trying to recover more money than we have on our books. And if we get it from the sale, as opposed to stranded investment, great. Matter of fact, I think that would help everybody."
Third, there is ample evidence in the record that the Transaction Agreement was indeed "a bona fide third-party transaction under a competitive offering" as specified in subsection (h)(1). A Center-Point investment banker testified that the bidding process for Genco consisted of contacting 107 potential buyers; 90 expressed an interest in receiving a teaser letter; of those 90, confidentiality agreements were negotiated with 38; and 17 expressed an interest in bidding. Ten parties submitted "first round indicative interest proposals"; six of those ten had an opportunity to conduct a full due diligence review of Genco
Fourth, as we read Chapter 39, it does not give any preference to the PSV method in this case simply because CenterPoint sought recovery of stranded costs under that method. We disagree with Center-Point and the PUC to the extent that they argue the utility may choose the valuation method even when the method results in higher stranded costs than another readily available method. In these circumstances, the utility should not be allowed to increase its stranded costs by choosing the market valuation method that results in the smaller measure of market value. While Section 39.262(h) provides that "the affiliated power generation company shall quantify its stranded costs using one or more of the following methods," other provisions make clear that the PUC ultimately determines stranded costs under Chapter 39 and the rates and charges needed to recoup them.
The Act required utilities to undertake certain efforts to mitigate stranded costs in the 1998-2001 time frame. Section 39.254 directed utilities to use these efforts to reduce the book value of generation assets. Because stranded costs represent the difference between book value and market value, a reduction in the book value of generation assets had the effect of reducing stranded costs. The Act directed utilities to redirect depreciation expenses from transmission and distribution assets to generation assets, and to apply certain "excess earnings" to reduce the book value of generation assets.
Prior to January 1, 2002, CenterPoint engaged in mitigation efforts by redirecting $841 million in depreciation and applying $1.13 billion in excess earnings to reduce the net book value (NBV) of its generation assets.
Section 39.201(h) required the PUC to make a determination of estimated stranded costs based on the ECOM model using "updated company-specific inputs." As noted above, Section 39.201 provided for interim rates during the 2002-2003 period, until the calculation of final stranded costs in the Section 39.262 true-up proceeding. The projections indicated that CenterPoint would have no stranded costs.
The EMCs increased the NBV of CenterPoint's generation assets on a dollar-for-dollar basis. However, the PUC concedes that the ECOM model assumptions underlying the 2001 finding that Center-Point would have no stranded costs — the finding that the PUC used to justify the EMCs — proved to be false. At the 2004 true-up proceeding, CenterPoint established that it had substantial stranded costs.
In a mandamus proceeding, CenterPoint objected to the order requiring EMCs. In that proceeding, the PUC represented to this Court in its briefing and at oral argument that CenterPoint could recoup the EMC payments in the true-up proceeding now under review if CenterPoint was ultimately determined to have stranded costs. This Court denied mandamus relief,
In the true-up proceeding, CenterPoint contended all the EMCs it had already paid retailers could be recovered as stranded costs. CenterPoint argued it should not be penalized for following the PUC's mistaken decision to order the EMCs. Intervenor City of Houston argued that CenterPoint should not be allowed to recover $385 million in EMCs paid to its retail affiliate, RERS. The PUC rejected this argument, finding "no legal basis for the recommended disallowance" and declining to "penalize CenterPoint for following
The trial court agreed with the PUC majority on this issue. The court of appeals, however, agreed with the dissenting commissioner and held that CenterPoint could not recoup the EMCs paid to RERS. Although the court of appeals assumed that CenterPoint and RERS are "completely separate entities,"
We reverse the court of appeals and affirm the PUC on this issue. We need not decide whether the PUC could ever order excess mitigation credits. Even if the PUC theoretically possessed the legal authority to order EMCs, as a factual matter the PUC should not have done so in this case. The credits were ordered only because the ECOM model incorrectly predicted that CenterPoint would have no stranded costs. CenterPoint should recover whatever stranded costs it would have recovered if the EMCs had never been paid. EMCs paid to RERS had the same dollar-for-dollar impact on CenterPoint's stranded costs as EMCs paid to unaffiliated retailers. Intervenors concede in their brief that as to EMC payments generally, "[f]or every dollar of EMC payments made, CenterPoint wrote up its NBV by one dollar, thus increasing potential stranded costs," and that as to EMC payments to RERS in particular, "every dollar that CenterPoint paid to [RERS] resulted in CenterPoint writing up NBV by an equal amount." In either case, the purpose of the EMCs was to increase the NBV of CenterPoint's generation assets. The PUC did not err, therefore, in declining to adjust stranded costs by disregarding any of the EMCs paid by CenterPoint, and Intervenors fail to demonstrate a sound legal or factual basis for deducting the EMCs that were paid to RERS.
We cannot agree with the court of appeals that the payment of EMCs to CenterPoint's affiliate RERS merits special treatment. Chapter 39, in its express measures for recovering stranded costs and preventing the over-recovery of stranded costs, makes no distinction between affiliated and unaffiliated electric retailers that would warrant special treatment of the EMCs paid to RERs. The EMCs were simply an interim and ultimately unwarranted effort to reverse what the PUC perceived to be an over-recovery of stranded costs before the final true-up. There is no express statutory provision allowing such credits, as the Third Court of Appeals noted in holding that Chapter 39 did not permit them. However, Section 39.201 does provide for the transmission and distribution utility to impose competition transition charges, based on interim estimates of stranded costs. Section 39.107(d) provides that these charges are made to "a customer's retail electric provider." These provisions make no exception or distinction for an affiliated retail electric provider. If the interim CTCs result in an over-recovery of stranded costs, Sections 39.201(l) and 39.262(c) provide for the transmission and distribution utility to refund stranded costs by reducing the CTCs or rates charged to retail
Because the EMCs, by design, had the effect of increasing the NBV of generation assets regardless of whether they were directed to an affiliated or unaffiliated retail electric provider, and because such an increase in NBV correspondingly increased the amount of stranded costs under the relevant provisions of Chapter 39, the PUC did not err in refusing to reduce stranded costs by the portion of the EMCs paid to RERS.
CenterPoint and Intervenors complain that the PUC erred in its treatment of the "RRI Option." Under the business separation plan, Reliant Energy, Inc. conveyed its generation assets to a subsidiary, Genco. Reliant Energy changed its name to CenterPoint. As discussed above, CenterPoint spun off approximately 19 percent of the shares of Genco to CenterPoint's shareholders. CenterPoint also spun off a company named Reliant Resources, Inc. (RRI), by selling approximately 20 percent of the shares in RRI in an initial public offering, with CenterPoint retaining about 80 percent of RRI.
As part of the business separation plan, which the PUC approved in a separate proceeding, RRI received an option to purchase CenterPoint's shares in Genco. The Option expired on January 24, 2004. The Option price was set at the price for Genco that was to be determined at the true-up proceeding.
Under its "primary holding" that rejected the use of the PSV method, the PUC employed an extra-statutory method that considered various "data points" for determining market value, as described above. Under this holding, the PUC concluded that its method of calculating fair market value accounted for the effect of the RRI Option. It therefore held under its primary holding that no adjustment to NBV relating to the RRI Option was necessary. The trial court and the court of appeals
Intervenors complain that if the Court agrees with the primary holding rejecting the use of the PSV method, the PUC nevertheless erred in refusing to make a requested deduction from the NBV calculation to reflect the RRI Option. We need not reach this issue because we reject the primary holding. CenterPoint complains that if as it contends the PSV method must be used, the PUC erred in concluding under its alternative holding that an adjustment should be made to NBV to reflect the RRI option. Again, this issue is moot
However, Intervenors argue that "[r]egardless of how market value is determined," an adjustment to NBV should be made for the RRI Option. Insofar as Intervenors argue an adjustment to NBV should be made for the RRI Option even if we agree with them that the sale of assets method should be used to determine market value,
The PUC reasoned in its alternative holding that if it is required to use the PSV method of calculating market value, an adjustment should be made to NBV to reflect the RRI option. It made the adjustment under PURA Section 39.252(d), which provides:
Applying this provision, the PUC found that CenterPoint had received no compensation for the Option conveyed to RRI and that the Option placed restrictions on the management and operations of Genco that "were not commercially reasonable and did not represent normal business practices."
The PUC could consider the commercial reasonableness of the RRI Option in determining NBV. The PUC adjusted NBV in making the stranded cost determination, after finding that the conveyance of the Option was commercially unreasonable and did not represent normal business practices. Section 39.252(d) expressly directs the PUC, when making the stranded cost determination, to consider whether the utility used "commercially reasonable means" and "normal business practices" to reduce stranded costs. Since Section 39.252(d) bars the PUC from adjusting the market value component of stranded costs, it necessarily authorizes an adjustment to NBV, the other principal component of stranded costs.
CenterPoint points out that in an earlier proceeding approving the business separation plan, the PUC noted that the Option "was an integral part" of the plan and "meets the separation requirements in PURA § 39.051." Section 39.051, however, is the provision requiring the separation of the utility into three separate entities. The PUC's conclusion that the business separation plan complied with this provision did not necessarily mean that CenterPoint had taken all reasonable efforts to minimize stranded costs under Section 39.252(d). Indeed, in the earlier proceeding the PUC expressly stated that it was not approving the RRI Option and other agreements that had not yet been finalized, and that its approval of the business separation plan "does not preclude a review in the 2004 true-up proceeding of whether [Center-Point]
The PUC considered evidence that the grant of the RRI option was not a normal business practice and had an adverse effect on the value of the generation assets. One of Genco's own SEC filings conceded that the Option limited Genco's ability to (1) merge with another company, (2) sell assets, (3) enter into long-term contracts, (4) engage in other businesses, (5) construct or acquire new plant or capacity, (6) engage in certain hedging activities, (7) encumber assets, (8) issue new securities, (9) pay special dividends, and (10) engage in certain transactions with affiliates. The report states that these restrictions "may adversely affect our ability to compete with companies that are not subject to similar restrictions." The PUC also considered expert testimony that the Option was very unusual and did not represent normal business practices, gave RRI an incentive to reduce the value of Genco, was viewed negatively in the investment community, and limited Genco's upside potential. The last point seems obvious, since RRI could derail an outside offer for Genco above the option price by exercising the Option, assuming that RRI had the funds. CenterPoint's own financial advisor on the spinoff of Genco acknowledged in a presentation that the "RRI option limits upside potential." Michael Gorman, a witness for Intervenors, opined that the Option was unreasonable because it "essentially transferred significant control of [Genco] to RRI," which then had "an incentive to minimize the value of" Genco, an incentive "diametrically opposite of [CenterPoint's] obligation to protect the value of [Genco] and mitigate stranded costs." Another witness for Intervenors, William Purcell, testified that the Option "gave RRI in effect the right of first refusal to buy" Genco, which "acted as a deterrent for [Genco or CenterPoint] to receive independent third party purchase bids or indications of interest — and, accordingly, was a drag on [Genco's] stock price."
Gorman calculated the "intrinsic value" of the Option at approximately $330 million. He made further adjustments to this figure that the PUC rejected because they did not reflect the value the Option would have had in an arms-length transaction. The PUC valued the Option at $330,314,000 and determined the NBV should be reduced by this amount, and further grossed up this amount by an additional $177,874,089 to reflect accumulated deferred federal income taxes.
Summarizing Gorman's approach (and ignoring that the PUC only agreed with part of his methodology), the Option was priced at the market price to be determined under the PSV method, with an adjustment for a control premium of up to 10 percent to be determined by the PUC, as Section 39.262(h)(3) specifies. Gorman, however, believed that the actual control premium should be 30 percent, based on premiums over market prices paid in corporate acquisitions of similar companies. The difference between the 30 percent market premium and statutory premium was therefore 20 percent. Gorman determined that Genco's future market value at the Option exercise date would approximately equal its book value of $2.9 billion, took 20 percent of that number ($580 million) to reflect the 20 percent difference in control premiums, took 81 percent of that figure to reflect CenterPoint's ownership in Genco ($469.8 million) and then discounted that value back to the date the Option was granted to arrive at $330 million as the Option's "intrinsic value."
We have reviewed the administrative record and conclude that while substantial evidence supports the PUC's conclusions that the Option was not commercially reasonable
The PUC apparently believed that the $330 million dollar figure derived from Gorman's testimony reflected the negative impact of the Option on the market value of Genco. In a subheading on "Market Value," the PUC found that "the entire [market] valuation process was not commercially reasonable," and accordingly made an adjustment to NBV as required by Section 39.252(d). Further, the PUC explained that no adjustment to market value under its primary holding was needed because the stock price selected under that method, which included consideration of the market control premium, "takes into consideration the operational constraints placed upon [Genco] by the Option and the control premium." When it turned to NBV, the PUC made an adjustment for the Option because of its effect on market value, reasoning that "Gorman calculated the amount of the option's below-market pricing by taking the difference between the 10 percent maximum control premium RRI would have had to pay if it had exercised the option, and an average industry control premium of 30 percent, which RRI would likely have had to pay in a bona fide third-party transaction." The PUC apparently concluded that the Option depressed the market value of Genco stock by $330 million, since under Gorman's testimony, as analyzed and accepted in part by the PUC, this amount arguably reflected the difference between what a third-party bid for the company might have brought and the ceiling on market value imposed by the Option.
However, this analysis breaks down if the sale of assets method is used, because the actual sale of Genco took place months after the Option expired. The Option expired in January 2004, and the sale of Genco assets occurred in December 2004 and April 2005. There is no evidence that the Option had an impact on the value of the assets sold under the Transaction Agreement. As the PUC notes in its brief to this Court, "The announced future sales price for Genco occurred months after the Option expired. Moreover, the sale itself resolved the uncertainty about the future of the company. Thus, that price was unaffected by the unreasonableness of the expired Option." The court of appeals similarly noted that the offer to purchase Genco in the Transaction Agreement "came several months after the option expired and after the restrictions placed upon Genco by the option had ended. As a result, any detrimental effect on Genco's value resulting from the option should have dissipated."
Intervenors nevertheless argue that if CenterPoint had sold the Option instead of imprudently giving it away, the sale of that asset could have been used to reduce net book value and thus mitigate stranded costs. But this simply assumes that the Option could have been sold. There was no evidence that RERS or any third party was interested in purchasing the Option,
Accordingly, on remand, the PUC should not make an adjustment to NBV for the RRI Option in conjunction with its use of the sale of assets method to determine market value.
CenterPoint complains that the PUC erred in reducing stranded costs attributable to depreciation on generation assets. The PUC reduced CenterPoint's stranded costs by reducing the NBV of its generation assets by approximately $378 million, a figure representing depreciation on those assets for years 2002 and 2003. The PUC reasoned that this adjustment was necessary to prevent an excessive recovery of stranded costs. It noted that under Section 39.262(a), a utility "may not be permitted to overrecover stranded costs through the procedures established by this section," which governs the final stranded cost and capacity auction true-ups.
Specifically, the PUC found it inappropriate
The PUC therefore held that an "adjustment" to NBV must be made in the stranded cost calculation to prevent the perceived "double recovery." The trial court and the court of appeals
We agree with CenterPoint that the Commission misread the relevant provisions of Chapter 39. As explained above, Chapter 39 requires both a stranded cost true-up and a capacity auction true-up. Nothing in the world of business or accounting requires both true-ups to transition a regulated industry to a more competitive market. But the Legislature provided for both and requires both. As we noted in our earlier CenterPoint decision, "the Legislature chose not to include the capacity auction true-up amount in its definition of stranded costs or to incorporate it into the methods it prescribes for calculating stranded costs."
On the other hand, as we have previously explained, the capacity auction true-up "guarantees consumers and power companies that the power company will receive no more and no less than a margin predetermined by the PUC in 2001 when the ECOM model was run in compliance with section 39.201."
Critically, the capacity auction true-up amount is determined for the years 2002 and 2003. We have so stated, explaining that this true-up consists of "the difference between the price of power obtained through the capacity auctions and the power cost projections that were employed in the 2001 ECOM model for the years 2002 and 2003."
The PUC apparently reasoned that the capacity auction true-up is based on the ECOM market revenue projections used to set interim rates in the 2001 Section 39.201 proceeding. As discussed further below, we agree with the Order that these revenue projections "assumed the continuation of regulation." Under traditional rate regulation, rates are set to allow the utility to recover a reasonable return on its capital investments.
We think the Commission erred in its analysis. Any utility will eventually retire all of its stranded costs, or any other capital investment or portion thereof, if it survives deregulation and continues to operate at a profit for a sufficient period of time. "Depreciation" is a general term referring to the accounting practice of spreading an asset's cost over the projected useful life of the asset or some other period.
Intervenors contend in their brief: "The problem the Commission addressed in the true-up award was that because NBV was frozen as of December 31, 2001, it could not be reduced by the $378 million in depreciation expense that CenterPoint indisputably collected through the capacity auction true-up as a contribution to its fixed costs." The problem with this analysis is that, by statutory definition, the NBV component of stranded costs is frozen as of December 31, 2001, and the PUC's adjustment effectively moved that date in violation of the statute.
Intervenors argue that the Commission erred in not requiring CenterPoint
Inclusion of CWIP increased stranded costs by about $110 million. The PUC's Substantive Rule 25.263(g)(2)(A)
In addressing Intervenors' arguments, the PUC noted that "[n]o party claimed accounting mistakes or imprudence on any specific project included in CWIP," and found "there is no evidence of any accounting discrepancies or any failure to follow GAAP in connection with these balances." It recognized that under PURA § 36.054, applicable to general ratemaking, CWIP can be included in the rate base only if "(1) necessary for the utility's financial integrity and (2) not inefficiently or imprudently planned or managed." The PUC, however, declined Intervenors' request to apply these additional requirements because Chapter 39 is concerned with the unique matter of stranded costs measured by the difference between the NBV of generation assets and market value, while general ratemaking applies ratemaking standards to determine what amounts of book value may be included in the rate base and the appropriate rate of return on that rate base. It also noted that "[o]ne significant difference between a traditional rate case and this proceeding . . . is that whereas under traditional regulation a utility is allowed to file rate cases on a recurring basis into the future, this proceeding is strictly a one-time phenomenon." In other words, CWIP can be recovered under Section 36.054 in the exceptional case if the requirements of that provision are met; otherwise, the utility can simply seek recovery for the construction project in a future rate case. There is no analogous recurring procedure for the recovery of stranded costs.
Intervenors argue that under Section 39.260(a), "[t]he definition and identification of invested capital and other terms. . . that affect the net book value of generation assets . . . shall be treated in accordance with generally accepted accounting principles as modified by regulatory accounting rules generally applicable to utilities." The PUC did not agree that in the calculation of stranded costs this provision requires the application of Section 36.054's special rules regarding CWIP. It noted that Section 39.260(a) did not expressly incorporate those particular standards. The PUC further reasoned:
We cannot say the Commission's analysis is legally or factually flawed, and we defer to the Commission on this technical issue.
CenterPoint complains that the court of appeals and the PUC erred in concluding that an adjustment to the capacity auction price should be made in calculating the capacity auction true-up under Section 39.262(d). We agree with CenterPoint.
Genco became the affiliated power-generation company of CenterPoint in 2001. Section 39.153 required Genco to auction "at least 60 days before [January 1, 2002], entitlements to at least 15 percent of [its] Texas jurisdictional installed generation capacity."
Under Section 39.201, the PUC approved rates intended to cover expected stranded costs and other charges. Stranded costs were estimated based on "the ECOM administrative model"
Section 39.262(d)(2) required a capacity auction true-up at the final true-up proceeding. Section 39.262(d) states:
The final fuel balance of subpart (1), which is summed with the capacity auction true-up amount, is not at issue in this appeal. Under subpart (2), the power-generation company (Genco) bills the transmission and distribution company (CenterPoint) if revenues as determined by the capacity auction price are less than the revenues predicted by the ECOM model. The amount billed to the transmission and distribution company can then be recovered from consumers through adjustment of the nonbypassable delivery rates.
Under this formula, market revenues "as determined from capacity auctions" is a term of art and is a proxy for actual market revenues of the utility during the relevant period. Under the Rule, market revenues consist of the "capacity auction
In its Order the PUC stated that "the purpose of the capacity auction true-up is to ensure that utilities receive the margins predicted in the ECOM model which assumed the continuation of regulation." We agree, having previously noted that the capacity auction true-up "guarantees consumers and power companies that the power company will receive no more and no less than a margin predetermined by the Commission in 2001 when the ECOM model was run in compliance with section 39.201."
Sections 39.153(e) and (f) required the PUC to adopt rules governing the statutory capacity auctions. The PUC adopted rules governing the auctions in many particulars, covering the time of sale, the type of products sold, and the terms of the sales.
Genco offered the required 15 percent of its capacity in the four product categories in its statutory capacity auctions and sold all the entitlements for at least one month in 2002 and 2003 for each product category except for gas-intermediate in 2003. Genco made proposals to facilitate the auction for gas-intermediate, two of which were approved by the PUC, that included cut-rate pricing for as little as one cent for kilowatt-month, but Genco was ultimately unsuccessful in meeting the safe-harbor requirement that it sell all entitlements to
The Commission found that Genco had sold only 65 percent of the capacity it was required to sell under the 15 percent requirement of Section 39.153, and less than half the gas-intermediate capacity required of Commission rules. However, Genco correctly points out that it would have complied with the safe harbor provisions if it had succeeded in selling additional entitlements in one product category for $5,250. Based on this failure, the PUC concluded that Genco had not complied with PURA Section 39.153(a) and therefore its formula under Rule 25.263(i) could not be used. It then proceeded to consider an alternative "proper method" for determining the capacity auction true-up amount, one that in the eyes of the PUC would avoid "the bias created by the failure of [Genco] to auction a full 15 percent of its auction products."
The PUC considered various proposals but adopted the approach of an Intervenor witness, Dennis Goins, who proposed "that the capacity auction price used in the formula should be defined as the average price of all capacity products sold in the PUC and private auctions." Under this formula, the capacity auction true-up amount was reduced by $439,744,218. The district court reversed the PUC on this issue, but the court of appeals agreed with the PUC and reinstated this disallowance.
We conclude that the court of appeals and the PUC erred in reducing the capacity auction true-up amount as described above. The capacity auction true-up amount should not be reduced by over $400 million because Genco was unable to sell $5000 worth of one subcategory of its generation capacity at auction. While Section 39.153 specifies that the utility sell 15 percent of its generating capacity at auction, the record indicates that Genco made a good faith effort to comply with this statute and was simply unable to sell by auction, at any price, the amount of one product category required by PUC rules. It points out that no utility was able to sell all its gas-intermediate entitlements for even one month in 2003. We avoid statutory constructions that impose an impossible condition.
Further, Section 39.262 does not state that the capacity auction price specified therein should be ignored because of a trivial noncompliance with rules promulgated under Section 39.153. Nothing in Chapter 39 requires such a result. In the portion of the Order discussing the issue, the PUC conceded, "Neither PURA nor the Commission's rules specify what happens if a company fails to meet the 15 percent sales requirement or the safe-harbor provisions." The capacity auction true-up in Section 39.262 is not conditioned
Section 39.262 does, however, expressly require the use of the "price of power obtained through the capacity auctions under Sections 39.153 and 39.156."
Section 39.262 unambiguously specifies that the statutory capacity auction price, not some other blended price the PUC finds more appropriate, must be used in calculating the capacity auction true-up amount. The PUC's Rule 25.263(i), the validity of which is not challenged by any party,
Intervenors complain that the PUC erred in allowing CenterPoint to recover $168 million in interest on the capacity auction true-up award. The trial court and court of appeals
In Texas Industrial Energy Consumers v. CenterPoint Houston Electric, LLC, we recently held that interest on the capacity auction true-up and other non-stranded costs awarded in a Section 39.262 true-up proceeding was recoverable.
While, as discussed above, general ratemaking principles need not always be applied to a Chapter 39 true-up proceeding, we again see no valid reason the PUC cannot provide for interest on true-up balances under Rule 25.263(l)(3), including interest on the capacity auction true-up balance. The parties in TIEC challenged the amount of interest specified under Rule 25.263 (l)(3), and did not necessarily question the authority vel non of the PUC to award interest, but in today's case we see no error in the PUC's decision to award interest on the capacity auction true-up to reflect the time value of money. Since, as discussed above, this true-up award is designed to assure the recovery of revenues projected in the ECOM model for 2002 and 2003, the PUC reasonably concluded that a full recovery of this amount must include interest to reflect the time value of money. It correctly found in its Order: "Awarding the time value of the capacity auction true-up award puts the joint applicants in the same economic position they would have been in had they received this amount in 2002 and 2003." Intervenors provide no persuasive reason that interest on the capacity auction true-up cannot be awarded in this case as in other cases where utilities are allowed to recover costs with interest.
We affirm the court of appeals' judgment in part and reverse it in part. We remand this case to the Commission for
Section 39.263 pertains to certain environmental cleanup costs.
As with the federal securities statutes, the Texas definition of "sale" of a security is broad, including "every disposition" and "any transfer or agreement to transfer." See Tex. Capital Sec., Inc. v. Sandefer, 58 S.W.3d 760, 775 (Tex.App.-Houston [1st Dist.] 2001, pet. denied) ("[The Texas Legislature] broadly defined `sale,' `sell,' and `security.'"); 11 WILLIAM V. DORSANEO & PETER WINSHIP, TEXAS LITIGATION GUIDE § 171.03[1][a] (interpreting the statute as including a "for value" requirement). No Texas court has addressed whether a stock distribution though a stock dividend constitutes a "sale," although a court has said that the exercise of a stock option will constitute a "sale" under the Texas Act. See Key Energy Servs., Inc. v. Eustace, 290 S.W.3d 332, 342-43 (Tex.App.-Eastland 2009, no pet.) ("[T]he grant of an employee stock option on a covered security is a sale of that security.").
The Securities Act of 1933 defines "sale" of a security as including "every contract of sale or disposition of a security or interest in a security, for value." 15 U.S.C § 77b(a)(3). "The term `offer to sell', `offer for sale', or `offer' shall include every attempt or offer to dispose of, or solicitation of an offer to buy, a security or interest in a security, for value." Id. The Securities Exchange Act of 1934 defines "sale" of a security to include "any contract to sell or otherwise dispose of." Id. § 78c(a)(14).
Some federal courts have determined that a spin-off through a stock distribution constitutes a "sale" under both the 1933 Securities Act and the 1934 Securities Exchange Act. Int'l Controls Corp. v. Vesco, 490 F.2d 1334, 1343-44 (2d Cir.1974) (discussing 1934 Act); S.E.C. v. Datronics Eng'rs, Inc., 490 F.2d 250, 253-54 (4th Cir.1973) (discussing 1933 Act); S.E.C. v. Harwyn Indus. Corp., 326 F.Supp. 943, 953-54 (S.D.N.Y.1971) (same); see also S.E.C. v. Sierra Brokerage Servs. Inc., 608 F.Supp.2d 923, 940-44 (S.D.Ohio 2009) (considering "gifts" of securities to former directors and shareholders as "sales" where defendant schemed to create public companies without registration and then later transfer control for a fee). Other federal circuits have held to the contrary. The Fifth Circuit has held that an asset-for-stock exchange is not a "sale" within the meaning of Section 10(b) of the 1934 Act where the parties are not at arms length. Rathborne v. Rathborne, 683 F.2d 914, 918 (5th Cir.1982) ("[A] transfer of securities from a wholly controlled subsidiary to its parent or between two corporations wholly controlled by a third does not amount to a statutory purchase or sale."); see also Blau v. Mission Corp., 212 F.2d 77, 80 (2d Cir.1954) (determining stock-exchanges between corporations with shared ownership were not "sales" within the meaning of Section 16(b) of the 1934 Act because the transaction was "a mere transfer between corporate pockets"). Several more recent cases declined to characterize spin-offs as sales, of-ten considering the earlier cases' reasoning as a means to prevent backdoor IPOs without registration and making information available to the public. See Isquith v. Caremark Int'l, Inc., No. 94 C 5534, 1997 WL 162881, at *6 (N.D.Ill. March 26, 1997) (distinguishing Harwyn and Datronics as SEC enforcement actions, as opposed to shareholder suits), aff'd, 136 F.3d 531 (7th Cir.1998); In re Union Carbide Corp. Consumer Prods. Bus. Sec. Litig., 676 F.Supp. 458, 475 (S.D.N.Y.1987) (noting that outside Harwyn and its progeny, "[t]here has been no other case demonstrating acceptance of such a broad view of `value'"); Fed. Ins. Co. v. Campbell Soup Co., No. Civ.A. 131-04, 2004 WL 1631405, at *9-13 (N.J.Sup.Ct. Law Div. July 2, 2004) ("Notwithstanding the[] broad statutory definition[], however, courts have still found that spin-offs generally do not constitute a sale of securities. . . . [T]his court finds that in all of the cases cited, the courts which did find a purchase and sale were struggling to do so in order to insure a remedy for a wrong . . . or the mischief of an unsympathetic defendant. . . would not go without a federal remedy."); see also In re Adelphia Commc'ns Corp. Sec. & Derivative Litig., 398 F.Supp.2d 244, 260 (S.D.N.Y.2005).
In 1997, the SEC issued a Staff Legal Bulletin No. 4, which attempted to explain the SEC's view of spin-offs in regards to registration under the 1933 Act. SEC Staff Legal Bulletin No. 4 (Sept. 16, 1997). The Bulletin begins by stating the general requirement that a subsidiary must register if the spin-off is a "sale." Id. The subsidiary does not have to register, and thus it logically follows no "sale" occurs, if: (1) the parent shareholders do not provide consideration for the spun-off shares; (2) the spin-off is pro-rata to the parent shareholders; (3) the parent provides adequate information about the spin-off and the subsidiary to its shareholders and the trading markets; (4) the parent has a valid business purpose for the spin-off; and (5) if the parent spins off "restricted securities," it held those securities for at least two years. Id.